All Our Services

BOOK A DEMO
Multi-Property Scan to CAD Floor Plan Production Across 7 Commercial & Industrial Parks

CASE STUDY | SCAN TO CAD SERVICES

Multi-Property Scan to CAD Floor Plan Production Across 7 Commercial & Industrial Parks

Scan to CAD | As-Built Floor Plans | Commercial & Industrial Properties | Pacific Northwest, USA

Project Overview

Project Type
Scan to CAD Floor Plans
Location
Pacific Northwest, USA
Properties
7 Commercial & Industrial Parks
Total Suites
41 Suites

Discipline: As-Built Documentation — CAD Floor Plan Production

Deliverable: Completed CAD floor plan files per suite, accurately matched to client CAD template

Input Data: Point cloud scan files and imported scan DWG files for each suite

Properties Covered: Commerce Center, Business Parks (x4), Industrial Park, Harbor Business Park — 41 suites total

Delivery Schedule: Phased: 10 suites by Week 1 — 15 suites by Week 2 — 15 suites by Week 3

eLogicTech delivered a large-scale Scan to CAD engagement for a US-based property design and management firm, converting point cloud scan data and DWG scan files across 41 individual suites spanning 7 commercial and industrial properties into production-ready CAD floor plans. All outputs were developed to precisely match the client’s established CAD template, enabling immediate use across their portfolio documentation and leasing workflows.

Client Challenge

Property portfolio documentation at scale creates a specific kind of coordination problem. Each suite has its own scan file, its own dimensions, its own quirks — and all of them need to land in a consistent, client-standard CAD format that can be dropped into leasing brochures, tenant coordination packages, or permit submissions without additional processing. When you’re working across 7 properties and 41 suites simultaneously, any inconsistency in template application, scale, or naming compounds quickly.

Key project challenges included:

  • Large volume of scope — 41 individual suites across 7 distinct commercial and industrial properties requiring coordinated production management
  • Scan data was not available for all properties at contract signing — files for 4 of the 7 properties were still to be received, requiring a phased intake and production workflow
  • All floor plans required precise template matching to the client’s established CAD standard — any deviation in layer structure, line weight, or annotation style would create rework across the portfolio
  • Suite sizes varied significantly — from under 1,000 sq ft to over 11,000 sq ft — requiring consistent scale and representation across a wide range of floor plan formats
  • Phased three-week delivery schedule required organized production batching and concurrent quality control as scan files came in across different timelines
  • Exterior elevations were explicitly out of scope — the boundary between in-scope floor plan work and excluded elevation work needed to be clearly maintained across all 41 suites

The client needed a CAD production partner capable of managing high-volume scan-to-CAD conversion across multiple properties in parallel, maintaining template consistency throughout, and delivering in organized weekly batches tied to scan file receipt.

Scope of Services

eLogicTech delivered end-to-end Scan to CAD floor plan production services across all 7 properties and 41 suites, from scan file intake through to final template-matched CAD deliverables.

Core Services Included:

  • Intake and processing of point cloud scan files and imported scan DWG files for each individual suite
  • CAD floor plan development for all 41 suites across 7 commercial and industrial properties, accurately matching the client’s CAD template
  • Phased production management — 10 suites in Week 1, 15 in Week 2, 15 in Week 3 — timed to scan data receipt
  • Template compliance review on all floor plans — layer structure, annotation style, line weights, and scale consistency maintained throughout
  • Multi-level quality control embedded at each weekly batch before delivery
  • Scope boundary management — floor plan production only, with exterior elevations explicitly excluded from all deliverables

Properties Covered:

Property Suites Status at Engagement
Commerce Center 1 Files received
Harbor Business Park 6 Files received
Harbor Warner Business Park 3 Files received
Mountain Business Park 6 Files received post-contract
Signal Hill Business Park I 5 Files received post-contract
Signal Hill Business Park II 5 Files received post-contract
Garden Grove Industrial Park 15 Files received post-contract

Technologies & Platforms:

AutoCAD
Floor Plan Production & Template Matching
Point Cloud / Scan DWG
Existing Conditions Data Source
CAD Template Standards
Client-Defined Layer & Annotation Standards

Scan to CAD Execution & Approach

A phased, scan-first workflow was applied across all 41 suites. Production was organized in weekly batches to align with the client’s scan file release schedule, with template compliance and QC checks built into each batch cycle — not deferred to a single end-stage review.

Phase 1 — Scan File Intake & Production Setup

  • Initial scan files and imported DWG files received for the first 3 properties and reviewed to understand suite extents, scan quality, and floor plan complexity
  • Client CAD template studied in detail — layer structure, line weights, annotation standards, and scale conventions confirmed before production began
  • Production batching plan established: Week 1 target of 10 suites prioritized against the received scan files
  • Phased receipt protocol agreed for the 4 remaining properties whose files were yet to be supplied

Phase 2 — CAD Floor Plan Production (Weeks 1–3)

  • Each suite’s scan data traced and interpreted to establish accurate floor plan geometry — walls, openings, partitions, and fixed elements captured to match physical conditions
  • All floor plans developed within the client’s CAD template, maintaining consistent layer structure, annotation, and line weight standards across all 41 suites
  • Suite areas ranging from under 1,000 sq ft to over 11,000 sq ft handled within the same template and production workflow without scale or format exceptions
  • Exterior elevations confirmed excluded from all outputs across every property

Phase 3 — QC Review & Batch Delivery

  • Each weekly batch reviewed internally for template compliance, geometric accuracy, and consistency before delivery
  • Deviations from the CAD template standard corrected within the batch cycle — not carried forward
  • Completed CAD floor plan files delivered in organized weekly batches aligned to the agreed schedule

Phase 4 — Remaining Property Intake & Final Delivery

  • Scan files for the 4 remaining properties received and added to the active production queue
  • Final batch completed and delivered within the Week 3 target, covering all 41 suites across 7 properties

Deliverables

  • 41 completed CAD floor plan files — one per suite — across 7 commercial and industrial properties
  • All floor plans developed from point cloud scan files and imported scan DWG data
  • All files accurately matched to the client’s established CAD template (layer structure, annotation, line weights, scale)
  • Delivered in three weekly batches: 10 suites by Week 1, 15 suites by Week 2, 15 suites by Week 3
  • Exterior elevations excluded from all deliverables per agreed scope boundary

Key Challenges & Solutions

Challenge: Scan files for 4 of 7 properties were not yet available at contract signing — production had to begin on received files while managing an open-ended intake queue for the remainder

Solution: A phased production model was structured from the outset: production commenced immediately on the 3 received property scan files, with the remaining 4 properties added to the active production queue as files arrived. This prevented schedule slippage on the early properties while keeping the overall delivery timeline on track.

Challenge: 41 suites across 7 distinct properties — varying in size from under 1,000 to over 11,000 sq ft — all required consistent CAD template compliance with no property-specific formatting exceptions

Solution: The client’s CAD template was studied in full before production began and applied uniformly across all 41 suites regardless of suite size or property type. Template compliance was reviewed at each weekly batch delivery — not at project close — ensuring consistency was maintained throughout the production run.

Challenge: High weekly output targets — 10 suites in Week 1, 15 per week in Weeks 2 and 3 — with embedded QC required at each batch, not just at final delivery

Solution: Production was organized as a continuous batching workflow with QC embedded at each cycle. This structure meant completed suites were reviewed, corrected if needed, and packaged for delivery each week — allowing the client to begin using earlier batches while remaining properties were still in production.

Measurable Outcomes & Client Benefits

Outcome Client Benefit
41 completed CAD floor plans delivered across 7 properties in 3 weekly batches Client’s entire commercial and industrial portfolio documented in usable CAD format within a three-week window
All floor plans matched to the client’s CAD template with no formatting exceptions across 41 suites Files dropped directly into the client’s leasing, documentation, and coordination workflows without reformatting or rework
Phased production model absorbed mid-engagement scan file receipts without schedule disruption Client avoided holding the full project start until all 7 property scan files were available — earlier properties delivered while later ones were still incoming
Weekly batch delivery enabled early access to completed floor plans during active production Client’s team could begin using Week 1 deliverables while Week 2 and 3 suites were still in production
Embedded per-batch QC ensured template consistency and accuracy across all 41 suites No end-stage consolidation rework required — each batch was ready to use on delivery

Client Feedback

 

“Managing scan-to-CAD production across this many suites and properties simultaneously is not straightforward. eLogicTech handled the phased file intake cleanly, kept all 41 floor plans consistent to our template, and delivered in organized weekly batches as agreed. The files were accurate, well-structured, and ready to use without additional formatting on our end.”

— Assistant CAD Manager, US-based Property Design & Management Firm, Pacific Northwest

Why eLogicTech

With over 25 years of experience in CAD and BIM documentation services for AEC and property professionals across North America, Australia, and the Middle East, eLogicTech understands that high-volume scan-to-CAD work is a production discipline, not just a technical one. Consistency of output across dozens of individual files, organized batch delivery, and strict template compliance are what separate a portfolio-ready deliverable from one that creates internal rework. Our teams are structured to handle both.